Fish Point Road Reconstruction Project
10/20 Construction Update
This season’s construction is nearing completion. With this in mind, we will not be doing regular weekly email updates moving forward. We will keep you informed if there are any noteworthy updates to share.
We are nearly done with paving.
Crosswalk striping is also expected today.
On Tuesday, we expect to do the striping of the center line, fog lines, and median on the north end.
Next week we will work on remaining “punch list” (repair/restoration) items.
This work is not expected to restrict vehicle access, though there will be brief delays as construction equipment moves through the area. Please plan ahead for delays.
10/17 Construction Update
We anticipate striping and paving in the coming days. Here is a look at the anticipated dates for this work:
Striping crosswalks: expected Thursday Oct 19 or Friday Oct 20.
Wear course of pavement: expected Friday Oct 20th on Fish Point Road from Huron St and heading north.
Remaining pavement striping: expected Tuesday Oct 24 or Wednesday Oct 25.
This work is not expected to restrict vehicle access, though there will be brief delays as construction equipment moves through the area. Please plan ahead for delays.
Project Highlights
Complete Street Reconstruction
Sidewalk replacement
Utility Replacement and Improvements
Sanitary sewer
Watermain
Storm sewer
Utility services
Street lights
Retaining Wall Replacement with Street Improvements
Phases
The project is divided into two construction phases:
Phase 1: 2021 Construction - includes Timber Trail, Millers Circle, Hidden Oaks Circle and Timberview Street and Omega Trail
Phase 2: 2023 Construction - includes all of Fish Point Road
Project Schedule
More Information
October 19, 2020 | Phase 1 Public Improvement Hearing
January 23, 2020 | Open House
Contact
Send an email to this address to sign up for the project email update list: info@fishpointproject.com
Project Helpline | 952-737-4683